Construction loan draw schedules: how draws are actually released

A sample draw schedule for a new house, then how inspection, percentage complete and paperwork decide when each draw funds.

September 24, 2026 · 12 min · Entrusted Capital underwriting desk

The short answer

A construction draw is released against the percentage of work actually in place, confirmed by an inspection, not against a date on a schedule. That is the single most important thing to understand before a build: the schedule says when you may request money, and the inspection decides whether you receive it.

A scheduled draw and a funded draw are different things

Almost every dispute on a construction loan comes from this gap. A draw schedule is a plan. It says that after the foundation, a given share of the budget becomes available. It is not a promise that money arrives on that date.

What releases money is an inspection confirming the work is in place. If the foundation is poured and the schedule says foundation, those agree and the draw funds. If the schedule says foundation and half of it is poured, the draw funds against half, or it waits.

Builders who have worked with banks know this. Borrowers funding their first build frequently do not, and they plan cash flow against the calendar rather than against completion.

A typical draw schedule for a new house

Sample schedules published by lenders and builder guides follow the same shape: a share at the foundation, the largest shares through framing and the rough-ins, and a smaller final draw held back for completion. Some lenders also release a small opening draw, about 5 to 10 percent, at or just after closing for permits, insurance and other soft costs.

Schedules vary by lender and by project, in the number of draws and in where each line sits, so treat the figures below as a pattern rather than a template. Whatever the split, the lender’s inspector releases each draw against completed work, not against the line on the schedule.

The schedule is attached to the loan, not agreed on the side. The builder prepares it against the line item budget, the lender approves the budget and the schedule before the first draw, and the approved version becomes part of the loan agreement that every later request is made against.

For a single family house with a 300,000 dollar construction budget, the published samples commonly break down as the table shows.

A sample draw schedule, from published lender and builder samples
DrawWhat it coversShare of budgetOn a $300,000 budget
FoundationClearing, footings, the slab or other foundation10 to 20%$30,000 to $60,000
Framing and dry-inWalls, roof and windows, so the house is weathertight20 to 30%$60,000 to $90,000
Rough-insPlumbing, electrical and HVAC before the walls close12 to 20%$36,000 to $60,000
Drywall and interiorDrywall, cabinets and counters, sometimes siding or stucco15 to 20%$45,000 to $60,000
FinishesTrim, paint, flooring, fixtures, appliances, often the driveway10 to 20%$30,000 to $60,000
FinalFinal inspection, certificate of occupancy, final survey5 to 10%$15,000 to $30,000

What the budget is for

The line item budget is the contract the draw schedule is measured against. It is not paperwork: it is the document that makes "fifty percent complete" mean something specific rather than something arguable.

A budget with twelve real lines beats one with four broad ones, because a broad line hides the exact thing an inspector has to confirm. Where a line is a lump sum, expect the draw against it to be conservative, which is not the lender being difficult; it is the lender being unable to see inside the number.

  • Line items specific enough that an inspector can confirm them from the site.
  • A contingency line, funded and untouched, because something will move.
  • A builder attached to the budget, with the scope they have actually agreed to.
  • Change orders documented as they happen rather than reconciled at the end.

Why money is held back

A construction lender does not fund a budget up front, because money released ahead of work is money at risk of never becoming a building. Every draw funded behind the work is a loan whose collateral is worth more than its balance, which is the entire discipline in one sentence.

This is also why a retainage or a final draw is normally held until completion. It is not the lender doubting the builder. It is the mechanism that makes finishing the last five percent worth more than walking away from it.

How to make draws fast

Draw speed is almost entirely within the borrower’s control, and it comes down to three habits.

Request against work that is finished, not work that is nearly finished. A draw that fails inspection costs more time than waiting two days would have.

Send the same documentation every time, in the same shape: invoices, lien waivers where required, and photographs. An inspector who can match the request to the site in five minutes releases in five minutes.

Flag changes before they are built. A change order approved in advance is an adjustment; the same change discovered at inspection is a problem that stops a draw while it is priced.

What a draw request actually contains

A draw is a claim that specific budget lines are complete to a specific percentage. The paperwork exists to make that claim checkable, and a complete request moves in days while an incomplete one sits.

  • The draw request itself: which line items, what percentage complete, what dollar amount against each.
  • Photographs, dated, showing the work described. Not a general site photo, the specific work being claimed.
  • Invoices from subcontractors and suppliers for the work in the request.
  • Lien waivers, conditional for the current draw and unconditional for the previous one. This is the piece most often missing and it is the piece that protects your title.
  • An updated schedule if anything has moved, because a lender reading a request against a stale schedule has to ask.

Lien waivers, and why they hold up money

Anyone who supplies labor or materials to a property can file a mechanics lien against it. A lien filed after your loan records can, in many states, take priority over it for work that began earlier. That is the risk the whole draw process is built to manage.

A conditional waiver says: when I am paid this amount for this work, I waive my lien rights to that extent. An unconditional waiver says: I have been paid and I waive them. The sequence is that you collect conditional waivers with the request and unconditional ones for the previous draw, which is how a lender confirms the last payment actually reached the people who did the work.

The failure mode is a general contractor who collects a draw and does not pay a subcontractor. The house looks finished, the lender has funded, and a plumber files a lien for 14,000 dollars against a property that is about to be refinanced. Waivers are tedious and they are the mechanism that prevents this.

Inspections, and what the inspector is actually doing

A draw inspection is not a building inspection. The municipal inspector checks code compliance; the draw inspector checks percentage complete against the budget. They happen on different schedules and they answer to different people.

The draw inspector’s job is narrow: walk the property, compare what exists to the budget lines being claimed, and report a percentage. They are not assessing quality, they are not approving the work, and they do not care whether the tile is the right color.

Two things follow. First, a claim that is ahead of the work will be caught, so do not round up. Second, work that is genuinely complete but not visible, insulation behind drywall, buried utilities, needs to be documented at the time rather than argued about afterward. Photograph it before it is covered.

Retainage, and the last ten percent

Most construction lending holds back a percentage of each draw, commonly five or ten percent, and releases it at completion. That is retainage, and it exists because the final ten percent of a project is where jobs get abandoned.

It has a consequence for your contractor relationship that is worth being explicit about: your builder is also carrying that holdback, and a builder who has not planned for it can run out of working capital near the end. Discussing retainage at contract signing rather than at draw four avoids a fight at the worst moment.

Release of retainage usually requires the certificate of occupancy, final lien waivers from everybody, and sometimes a final inspection. Assemble those in parallel rather than in sequence, because each one has its own queue.

The working capital nobody plans for

Draws are reimbursement. The work happens, then the money arrives. That means somebody funds the gap, and on most projects that somebody is you.

On a typical schedule the first draw comes after the first phase is complete, which can be three to six weeks into the job. Your builder wants a deposit, materials need buying, and the lender is not paying for any of it yet. A project with a 75,000 renovation budget can easily need 20,000 of working capital in the first month.

This is the most common reason a first-time build stalls, and it has nothing to do with the loan being wrong. Plan the gap, keep reserves after closing, and do not treat the loan amount as cash available.

Change orders, and the honest way to handle them

Every project changes. The question is whether the change is documented before the money is spent or argued about afterward.

A change order is a written amendment to the budget: what is changing, what it costs, and where the money comes from. If the total goes up, somebody funds the increase, and on most files that is the borrower rather than the loan, because the loan was sized against the original budget and the ceilings do not move just because the scope did.

The thing that causes real trouble is the undocumented change: a borrower upgrades finishes mid-project, spends draw money on lines that were not in the budget, and then requests a draw for work the schedule says should already be paid for. The inspector finds the mismatch, the draw stalls, and the builder stops.

The discipline is simple. Change the budget on paper first, get it acknowledged, then spend. A lender who sees changes coming can usually accommodate them; one who finds them in an inspection report cannot.

When a draw gets held, and what to do

Draws get held for a small number of reasons, and most of them are fixable the same day if you know what they are.

  • Missing unconditional waivers from the previous draw. The most common single cause, and entirely avoidable.
  • Claimed percentage ahead of the inspection. Resubmit at the real number rather than arguing; the inspector will be back.
  • An invoice that does not match a budget line. Usually a change order that was never written.
  • Insurance lapsed. Builders risk policies expire on a date, and projects run long. Put the expiry date on the calendar.
  • A lien filed on the property. Everything stops until it is resolved, which is what the waiver process exists to prevent.
  • Taxes unpaid. A lender will not advance into a position behind a tax lien.

How the money is actually held

It is worth understanding where the undrawn money sits, because it explains several things that otherwise look arbitrary.

The construction holdback is not in your account and it is not in a separate pot with your name on it. It is loan proceeds the lender has committed and not yet advanced. You are not paying interest on it in a well-structured loan, because interest accrues on the drawn balance rather than the commitment, and that is a question worth asking explicitly because not every lender does it that way.

This is also why a holdback larger than the loan is a structural problem rather than a paperwork one. If the construction budget exceeds the total loan, the holdback consumes the entire loan and the initial advance is zero. The loan is not wrong; the deal needs more equity.

And it is why a draw is not a new loan. No new underwriting, no new credit pull, no new title work. It is a release of money already committed against evidence that the milestone it was committed for has happened.

Sequencing the schedule so it works

A draw schedule that mirrors how construction actually spends money keeps a project liquid. One written for the lender’s convenience starves it.

The expensive phases are front-loaded more than people expect: site work, foundation and framing consume a large share of the budget early, while the later phases are lower cost and higher visibility. A schedule with five equal draws does not match that curve, and the builder funds the difference.

Better is a schedule with more draws, aligned to real milestones, so that money arrives closer to when it is spent. More draws mean more inspections and more paperwork, which is a genuine cost in time. Somewhere between five and eight on a single family build is usually the right trade.

Negotiate this at term sheet stage. Once the loan documents are signed the schedule is in them, and changing it afterward is an amendment rather than a conversation.

The paperwork that should exist before the first draw

Most draw friction is set up, or avoided, in the week after closing rather than in the week of the request.

  • A budget broken into lines a schedule can pay against, with quantities and prices, not lump sums.
  • A draw schedule both sides have agreed, mapped to real milestones rather than to equal fifths.
  • Builders risk insurance in force, with the lender named, and a calendar reminder for its expiry.
  • The contractor’s license and insurance certificates on file, so nobody is chasing them at draw one.
  • A single named person on each side who handles draws. Requests routed through whoever answers the phone move slowest.
  • Agreement on what photographs and waivers are expected, in writing, so the first request is complete rather than a learning exercise.

Also asked

Related questions

What is a typical draw schedule for a construction loan?
Published sample schedules for a new house commonly release about 10 to 20 percent of the construction budget at the foundation, 20 to 30 percent at framing and dry-in, 12 to 20 percent at the rough-ins, 15 to 20 percent at drywall and interior, 10 to 20 percent at finishes and the last 5 to 10 percent at completion. Schedules vary by lender and project, and each draw funds only after an inspector confirms the work.
What is a lien waiver and why does it hold up my draw?
Anyone who supplies labor or materials can file a mechanics lien against the property. Conditional waivers accompany the current request and unconditional waivers cover the previous one, which is how a lender confirms the last payment actually reached the people who did the work. Missing unconditional waivers are the single most common reason a draw stalls.
What is retainage?
A percentage of each draw, commonly five or ten, held back and released at completion, because the last stretch of a project is where jobs get abandoned. Your builder carries it too, so raise it at contract signing rather than at draw four. Release usually needs the certificate of occupancy and final waivers from everybody.
Do I pay interest on the money that is still held back?
In a well-structured loan, no: interest accrues on the drawn balance rather than the full commitment. Not every lender does it that way, so ask explicitly. On a deal with a large holdback the difference over twelve months is substantial.
How long does a draw take?
The variable is the inspection, not the paperwork. A request that matches completed work and arrives with its documentation moves quickly; one that arrives ahead of the work waits for the work.
Can I get money for materials I have not installed yet?
Sometimes, as a stored materials draw, and it is handled carefully because uninstalled material can leave a site. Where it is allowed it generally requires the material to be on site, secured and documented.
What happens if the budget turns out to be wrong?
It gets addressed rather than absorbed. A budget that is short is a fact about the project, and the earlier it is raised the more options exist: contingency, a revised scope, or additional capital. Discovering it at the final draw is the version with no options left.

Bring us the deal

Five questions, a soft pull, and a document checklist built from your answers.

More from the blog

Published by Entrusted Capital. Nothing here is a commitment to lend or an offer of credit, and every loan described is for business purposes and secured by non owner occupied property. Read it at entrusted-capital.com.